Context:
To
receive a presentation and scrutinise the preferred option for the
future of Tourism, Leisure, Culture and Youth Services (TLCY) and
to undertake pre-decision scrutiny of the evidence base and
business case to support the preferred option.
Key
Issues:
In
considering the need of the future delivery model of Tourism,
Leisure, Culture and Youth Services (TLCY) the following options
had been thoroughly researched and considered:
a)
Delivery Option One: Do
Nothing.
b)
Delivery Option Two:
Transform the Services ‘in house’.
c)
Delivery Option Three: Move the Services into an
Alternative Delivery Model (ADM).
d)
Delivery Option Four:
(a) Outsource the services to a private sector operator or (b)
existing Charitable Trust.
Member
Scrutiny:
- The
impact of VAT changes would breach the partial exemption
calculation in the sum of £200,000, but the Authority would
be required to repay a higher amount. The Authority would need to
be mindful when undertaking its investment which would limit the
Authority when it could make potential changes.
Monmouthshire’s VAT advisers have stated that it does
seriously breach Monmouthshire’s partial exemption
calculation and the recommendation would be that the ADM would be
the preferred alternative.
- In
response to a question raised regarding commercial failure, it was
noted that failure does occur in commercial ventures, the
differentiating factor is how the steps are taken to convert this
to success.
- These service areas have been one of the top contributors to the
Medium Term Financial Plan (MTFP).
- The
ADM will be customer focussed with the citizen being placed at the
centre of the service being provided. Initially there will be a
period of consolidation followed by providing sustainability and
optimising performance. Each building will require significant
investment to make the customer experience better.
- The
Head of Tourism Leisure, Culture & Youth is the chair of the
region for leisure and sports development and works collaboratively
with nearby local Authorities. The sharing of resources is a good
opportunity.
- With regard to the Service Level Agreements (SLAs) in schools, a
productive meeting had been held with the four head teachers and
the Chief Officer for Children and Young People. All agreed that there was a need to understand the
operational management of the sites. Schools have an opportunity to
generate income and will continue to do so.
- It
was a financial consideration for removing Events Management from
the ADM. One of the main considerations was that if we went outside
the Authority the VAT for the artists and infrastructure would have
to be paid. The ADM would not be best placed to host major events
due to the financial aspects required up front in order to
undertake this type of work. However, the ADM will still hold
community events.
- Clydach Ironworks and similar sites require development. It was noted that the countryside team has been
looking at these sites with a view to looking to work with partners
to establish sustainable development of these heritage
sites.
- In
response to a question regarding VAT at events, it was noted that
HMRC has made a ruling regarding cultural events in which a VAT
exemption will apply. However, HMRC
does not class a fireworks display as a cultural
activity.
- In
the early stages of the ADM the residual impact to the Council will
be mitigated through continuity of relationships through agreements
to continue operating back office services to the ADM. For example,
there will be a need to be mechanisms in place to pay staff,
suppliers and collect income. In time, the ADM could review this
process.
- £4.4 million maintenance backlog – priorities remain
around ensuring that the buildings are safe to use and the
Authority is spending money to maintain these
buildings. The current strategy is the
correct strategy for the amount of funding currently
available. In order to solve the
backlog issues, this will only arise from new ideas and new
investment.
- Business expertise is important.
- Partnership working will be undertaken.
- With regard to addressing grants and income streams, an officer
is in post with the correct qualifications and is working with the
teams with a view to identifying opportunities to generate
income.
- When the decision is made regarding the future of the ADM, a
coherent communication strategy will be formulated.
- In
response to a question of accountability with regard to the success
of the ADM, it was noted that there would be accountability at
Council level, the Teckel Board, and
the ADM Board, when established.
- It
was noted that Mounton House School has a relatively new gymnasium,
adequate parking and is out of town. It
would be a good location in which to hold junior league sporting
events. The school is used by other
authorities to hold sporting events. Work is currently ongoing on
the review of Additional Learning Needs.
- Ongoing knowledge transfer will be required to ensure that the
Authority learns from the success of the ADM and internalises this
knowledge within the Authority.
- In
terms of financial information for the new organisation, it is
critical. The ADM will be looking to re-arrange its cost centre
structure and be set up to run like a business. There will be
service level agreements with the Authority regarding back office
staff, with a view to monitoring and regulating costs.
Committee’s Conclusion:
- Difficult decisions will have to be made to ensure the
sustainability of discretionary services.
- The Committee discussed commercial risk / success and failure
and it is critical that the Authority learns from previous
mistakes.
- Residents need to be consulted and be the focal point of the new
model.
- Ensure sustainability and resilience of the services and ensure
performance is optimised.
- In the early stages there is a need to shape the commercial
culture using data to drive evidence based change and upgrading
some of the assets through managed maintenance.
- More work is required in terms of staffing capacity and to
ensure that the correct expertise is in place. However, the ADM is starting from a very sound
base with expertise in house regarding external
investment.
- Various options have been explored including a regional
model.
- The Authority’s environmental and heritage capital needs
to be protected for future generations.
- More work is required with regard to Service Level Agreements
(SLAs).
- Implementation and delivery of the ADM will be
crucial.
- Further work is required around governance to ensure maximum
accountability.
It was
proposed and seconded that Cabinet considers option 3, to move the
Services into an Alternative Delivery Model (ADM).
Upon being
put to the vote the following votes were recorded:
In favour
of the proposal - 10
Against the
proposal
- 0
Abstentions
- 2
The
proposition was carried.
We
recommended that Cabinet considers option 3, to move the Services
into an Alternative Delivery Model (ADM).
|