Minutes:
Context:
To scrutinise the proposed capital budget for 2018/19 and the indicative capital budgets for the three years 2019/20 to 2021/22.
Key Issues:
Capital Medium Term Financial Plan (MTFP) issues:
· The four year capital programme is reviewed annually and updated to take account of any new information that is relevant.
· The major component of the capital MTFP for the next few years is completion of the Council’s Tranche A Future schools programme. Colleagues are working through options in relation to a future Welsh Government Tranche B programme. No presumption has been made to add such costs into this next four year window as yet, as costs of proposals and their affordability are still to be established.
· As part of the 2017/18 budget setting process, Members identified five additional priorities that had not been costed at the time of budget setting, but for which they added an unhypothecated borrowing assumption of £500,000 per annum to the 2017/18 budget.
· During this year, some of those scheme costs have crystalised and the following indicates the related presumption within the capital programme together with an indication of the revenue consequences. In all cases an asset life of 25 years has been presumed:
- Monmouth Pool – commitment to re-provide the pool in Monmouth as a consequence of the Future Schools Programme, £7.3 million project afforded by £1.9 million Future Schools Programme, £985,000 Section 106 funding, core treasury funding in the region of £835,000, and £3.58 million prudential borrowing afforded by the Leisure Service through additional income predictions.
- Abergavenny Hub – commitment to re-provide the library with the One Stop Shop in Abergavenny to conclude the creation of a Hub in each of the towns. £2.3 million.
- Disabled Facilities Grants – the demand for grants is currently outstripping the budget, work is being undertaken to assess the level of investment required to maximize the impact and benefit for recipients. Members ultimately chose to put a one year commitment of £300,000 into the base capital programme in 2017/18.
- City Deal - 10 Authorities in the Cardiff City region are looking at a potential £1.2 billion City Deal. Agreement to commit to this programme is being sought across the region in January 2018 and would impact on the capital MTFP. The potential impact on individual authority budgets is currently being modelled in advance of decisions on specific projects and profiles in order for authorities to start reflecting the commitment in their MTFPs. The potential is for the 10 authorities to provide collectively £120 million over time, with individual contributions being reflective of populations. Monmouthshire’s indicative liability during the forthcoming capital MTFP is likely to be:
Contributions predicted during forthcoming MTFP window:
Year Amount
2018-19 £83,000
2019-20 £482,000
2020-21 £472,000
2021-22 £729,000
Contributions predicted following the MTFP window:
2022-23 £729,000
2023-24 £1,207,000
2024-25 £1,206,000
2025-26 £1,206,000
2026-27 £1,206,000
Total £7,320,000
MRP is presumed to start in the year after the contribution in made.
- J and E Block – the office rationalization programme is being considered to see if there is a solution that would enable the Magor and Usk sites to be consolidated, releasing funding to pay for the necessary investment to bring the blocks into use. The current presumption included in Treasury figures is £1.4million expenditure with MRP starting in 2020/21. No revenue savings from central accommodation or the Magor building have been presumed in the capital modelling, as those savings are unlikely to be realized until that building is vacated.
· A strategy that enables the core programme, Future Schools and the above schemes to be accommodated is being developed. Notwithstanding this, there will still remain a considerable number of pressures that sit outside of any potential to fund them within the Capital MTFP and this has significant risk associated with it. Cabinet has previously accepted this risk.
· The current policy is that further new schemes can only be added to the programme if the business case demonstrates that they are self- financing or the scheme is deemed a higher priority than current schemes in the programme and therefore displaces it.
In summary the following other issues and pressures have been identified:
· Long list of back log pressures – infrastructure, property, DDA work and Public rights of way. None of these pressures are included in the current capital MTFP, but this carries with it a considerable risk.
· In addition to this, there are various schemes / proposals (e.g. Alternative Delivery Model for Leisure, Tourism and Culture Services, Tranche B Future Schools, any enhanced DFG spending, waste fleet vehicle replacement, community amenity site enhancement) that could also have a capital consequence, but in advance of quantifying those or having Member consideration of these items, they are also excluded from current capital MTFP.
· Capital investment required to deliver revenue savings – this is principally in the area of office accommodation, social care, property investment and possibly Additional Learning Needs. The level of investment is currently being assessed. However, in accordance with the principle already set, if the schemes are not going to displace anything already in the programme then the cost of any additional borrowing will need to be netted off the saving to be made.
· The IT reserve is depleted so funding for any major new IT investment is limited. Any additional IT schemes will need to either be able to pay for themselves or displace other schemes in the programme.
· Base interest rates were increased by 0.25% to 0.5% on 2nd November 2017. That pressure is more likely to be felt in the Revenue MTFP as it will increase the cost of borrowing over time. However, it may also impact adversely upon the viability of capital business case developments and their ability to demonstrate self-affordability. Given this very recent change, it hasn’t been possible to fully work through the consequences in the initial revenue and capital MTFP. That will instead manifest itself through the budget setting process.
Member Scrutiny:
· There are numerous opportunities to review the capital programme as it is presented to select committee meetings every time there are amendments to it.
· The only change to this capital programme is the inclusion of the £300,000 for disabled facility grants. It is currently fixed at £600,000 but this will be increased to £900,000.
· In response to a question raised regarding the effects that Brexit might have on the Capital Budget, it was noted that Welsh Government provides the Authority with an element of core capital funding in which the Authority can chose to spend on within its schemes, which equates to £2,000,000. However, it is not known whether this is European funding. With regard to the 50% funding that comes from Welsh Government in relation to the Authority’s future schools aspirations, conversations around Tranche B have been held with Welsh Government and the consultation process is underway. There is unlikley to be any significant volatility to Monmouthshire’s Capital Programme as a consequence of Brexit.
· With regard to the constitutional governance issues in respect of the City Deal, it was noted that there were some matters that needed to be finalised.
Committee’s Conclusion:
The Select Committee had fully discussed the capital budget assumptions and priorities affecting the Select Committee’s portfolio area, however had no specific recommendations to make in terms of the approach being adopted.
|