Decision details

CHEPSTOW SCHOOL AND LEISURE CENTRE OUTDOOR PLAYING FACILITIES AND PITCHES

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

That Cabinet approve a capital budget of £101,907 (19% contribution) to be created in the 2021/22 financial year from the Council’s Capital Match Funding budget to match fund the upgrade and improvements of the outdoor playing facilities and pitches at Chepstow Comprehensive School and Leisure Centre, the remainder of the project costs, £433,058 (81% of total costs), being sourced through external grant funding.

 

That Cabinet agree that Officers progress and deliver the project, through partners Alliance Leisure and the UK Leisure Framework.

 

That Cabinet note the ongoing investments at Chepstow Leisure Centre, which when completed will represent a total investment of more than £1.6 million, including carbon reduction improvements to the leisure centre and outdoor facilities, upgrade of health and fitness equipment and the improvements to the outdoor playing facilities and pitches, as detailed in 3.2 of the report.

Publication date: 03/03/2022

Date of decision: 02/03/2022

Decided at meeting: 02/03/2022 - Cabinet