LEISURE CENTRE UPGRADES TO FACILITIES

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

That Cabinet recommends to Council to release the sum of £2.2m from capital receipts to fund the following investments to improve customer experience; Chepstow Leisure Centre – £0.5m to upgrade fitness equipment and minor centre refurbishments Abergavenny Leisure Centre – £1.7m to re-design the first floor to provide a new enhanced gym area and dedicated spin studio and exercise studio.

 

To pause any significant developments at Caldicot Leisure Centre pending the results of the Levelling up Grant Bid but to invest in some necessary upgrades to portable equipment and fitness class resources

Publication date: 07/07/2021

Date of decision: 07/07/2021

Decided at meeting: 07/07/2021 - Cabinet

Accompanying Documents: