Decision details

S106 Funding - Forensic Science Laboratory Site, Chepstow

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

That Council agrees to a budget of £77,736 being created in 2019/20 to fund the following projects and that this is funded by a corresponding contribution from the Section 106 balances held by the County Council from the Section 106 Agreement in relation to the Forensic Science Laboratory site in Chepstow.

 

That grants in the sums shown below be allocated to the following projects from the remaining balance of £77,736:

 

1. Upgrading of The Bayfield and the Danes Play Areas 46,736

2. Garden City Sensory Garden 6,000

3. Children’s Voices in Play project 25,000

 

Total 77,736

 

Publication date: 05/06/2019

Date of decision: 05/06/2019

Decided at meeting: 05/06/2019 - Cabinet

Accompanying Documents: