CAPITAL STRATEGY ASSESSMENT 2018-19 and DRAFT CAPITAL BUDGET PROPOSALS 2019-20 to 2022-23

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

That Cabinet considers the capital strategy requirements and assesses the preparedness of current practices to satisfy capital strategy compliance obligations for onward endorsement to Council as part of capital strategy report in January 2019.

 

That Cabinet considers the annual core capital programme identified in

Appendix 2 for 2019-20, together with the additions proposed in paras 6.14 to

6.18, and issues its draft capital budget proposals for 2019/20 to 2022/23 for consultation purposes.

 

That Cabinet reaffirms the principle that during the financial year, any new schemes volunteered can only be added to the programme if the business case demonstrates that they are self-financing or if the scheme is deemed a higher priority than current schemes in the programme and therefore displaces it.

 

When considering the relative merits of projects and potential displacement, that Cabinet consider the indicative priority matrix supplied in para 4.15, either endorsing or amending it for onward consideration by full Council.

 

That Cabinet considers the extent of proposed sale of assets captured in exempt Appendix 5, in order to support the capital programme, and that once agreed, no further options are considered for these assets.

 

That Cabinet note the potential forecast of capital receipt levels, prior to the consideration of using £75,000 of receipts balance to afford condition survey work to update historic condition survey information and a ceiling of capital receipts funding of £300k to assist with the business case affordability of

Severn View Residential Home replacement. Any excess of capital receipts generated thereafter is proposed to be applied by Treasury colleagues in a fashion that will mitigate minimum revenue provision costs and interest payments, to assist with revenue budget management. This is a change in capital receipt strategy to that applied in earmarking receipt generation to afford Members tranche A Future Schools aspirations. This will mean that any further school redevelopment will need to derive a greater extent of revenue headroom to afford the prudential borrowing financing of such developments.